TL;DR
Wallonia ordered Google to stop construction at its planned data centre in Farciennes after officials said a three-hectare building lacked proper planning permission. Google said it had paused work pending guidance; a court hearing over its challenge to a rejected water-cooling permit is scheduled for January.
Walloon regional authorities have ordered Google to suspend construction of its planned data centre in Farciennes, southern Belgium, saying a three-hectare building was erected without proper planning permission. Google said it paused work while awaiting further guidance. The order puts the project’s construction on hold as a separate court challenge over the site’s proposed water-cooling plan remains pending.
Get business pricing on networking and server gear
- Business-only prices and quantity discounts
- Tax-exempt purchasing
- Multiple users, one account, clear invoices
Regional inspectors visited the site on Thursday and told Google representatives to halt construction, the regional authority said. Nicolas Yernaux, a spokesman for Wallonia, told AFP that officials had identified what he called a “major offense”: construction of a building covering three hectares without the required permission. AFP reported the order on November 27, and the BBC reported Google’s response on November 29.
Google said it had paused work in Farciennes “pending additional guidance” and said it was committed to complying with local laws, according to the BBC. The reports available for this article cite statements from officials and Google; the underlying stop-work order was not found online. The authorities’ account is therefore reported as their stated reason for the action, rather than as an independently reviewed permit record.
The dispute also involves a proposed change to the facility’s cooling system. The original plan called for air cooling, according to Belgian media cited by AFP. Google later applied to use water from the nearby River Sambre. Regional authorities rejected that application over the summer after a dry spring intensified concerns about drawing water from the river. Google has challenged the refusal in court, with a hearing scheduled for January.

Water Permits Could Delay Capacity
The order shows how local planning decisions can interrupt construction of facilities intended to support cloud computing and AI services. A dispute over one building permit has stopped work at the Farciennes site while the parties seek further guidance and pursue the water-permit case. The sources do not say how long construction will be suspended or whether the building can later be approved.
The cooling question connects the project to local water availability. Data centres need to remove heat from their computer equipment, but the reporting does not state how much water Google proposed to draw from the Sambre or how the requested system would operate. The regional refusal followed concerns about drought, according to AFP. That makes the site’s water use a central part of the dispute, while leaving its specific projected demand unreported.
For cloud and AI customers, the immediate consequence is uncertainty about this project’s construction schedule. The reports do not establish that existing services are affected, or say whether Google has changed its broader capacity plans. More broadly, the case illustrates that new computing capacity depends on planning approval and access to infrastructure such as power and cooling, as well as on the construction itself.
Products Worth Considering

Logitech MX Master 4 for Mac

DJI Osmo Mobile 7P 3-Axis Smartphone Gimbal with Mic Mini Transmitter, Infinity Black

Jackery Explorer 300 Portable Power Station, 292Wh
As an affiliate, we earn on qualifying purchases.
From Air Cooling to River Water
Farciennes is a former mining site in Wallonia, Belgium. The data centre project’s original plans called for air cooling, according to Belgian media cited by AFP. Google later sought permission to use water from the nearby River Sambre for cooling. Regional officials refused the change during the summer, after a dry spring had raised concerns about taking water from the river, AFP reported.
Google challenged that refusal in court. Separately, Greenpeace Belgium said in a report this week that drone footage showed construction continuing, and alleged that the latest version of the planning permission had been revoked in August. Those claims are attributed to the environmental group; the reports do not include an independent review of the footage or the permit history.
Regional inspectors then visited the site on Thursday and informed Google representatives that construction should stop, according to the authority. The regional order concerns the building officials say lacked proper permission. AFP also reported that Finnish authorities halted work at two Google data centre sites in October, placing the Belgian action among several recent disputes over the construction of such facilities. The reporting does not establish that the Finnish cases have the same circumstances or legal basis.
““Pending additional guidance.””
— Google, as reported by the BBC
Permit Record and Water Demand
The reporting does not include the text of the stop-work order or the full planning-permit record. It is not yet clear whether authorities will allow the building to be legalised, what steps Google would need to take to resume construction, or how long the suspension will last.
The proposed volume of water from the Sambre has not been reported. The sources also do not resolve the dispute over whether construction was continuing after the relevant permission was revoked: Greenpeace alleged that work continued, while Google said it had paused work pending guidance. The timing and scope of Google’s pause relative to the inspection are not fully detailed in the reports.
January Hearing Will Test Water Plan
Google’s court challenge to Wallonia’s refusal of the water-cooling application is scheduled for a hearing in January 2027. That proceeding may clarify whether the requested cooling change can proceed. The available reporting does not say whether its outcome will resolve the separate planning-permission issue behind the stop-work order.
For construction to resume, the regional authorities’ guidance and the project’s permit status will matter. Neither officials nor Google have publicly detailed a timetable for resolving those points in the reports cited here. The site remains paused according to Google’s statement, while the January hearing is the next reported legal milestone.
Key Questions
Why did Wallonia order Google to stop construction?
Walloon authorities said a three-hectare building at the Farciennes site had been built without proper planning permission. A regional spokesman described it to AFP as a “major offense.”
Has Google stopped work at the site?
Google said it had paused work pending additional guidance, according to the BBC. Greenpeace Belgium had alleged that work was continuing before the stop-work order. The reports do not give a detailed timeline reconciling those accounts.
What does the River Sambre have to do with the dispute?
Google sought to change the project’s cooling plan from air cooling to water drawn from the Sambre. Regional officials refused the application over the summer amid concerns about drought, AFP reported. The amount of water Google proposed to use has not been reported.
When is the next court hearing?
A hearing in January 2027 is scheduled for Google’s challenge to the regional refusal of its water-cooling application. It is not clear whether that case will also settle the separate planning-permission issue.